Solving Resource-Constrained Project Scheduling Problem As a Sequence of Multi-Knapsack Problems

ŠEDA, M.

Anglický název

Solving Resource-Constrained Project Scheduling Problem As a Sequence of Multi-Knapsack Problems

Typ

Článek recenzovaný mimo WoS a Scopus

Jazyk

en

Originální abstrakt

This paper describes a new technique for solving the duration minimization in a resource-constrained network. It is based on a transformation of the resource-constrained project scheduling problem (RCPSP) to a sequence of (multi)knapsack problem (MKP) solutions. In the first part, three deterministic approaches are summarized and their time complexity is discussed. Due to the combinatorial nature of the problem for large projects with many constraints, heuristic techniques are applied. A genetic algorithm approach is proposed and compared with simulated annealing.

Klíčová slova anglicky

Resource-Constrained Project Scheduling Problem, Multi-Knapsack Problem

Vydáno

2006-07-01

ISSN

1790-0832

Ročník

3

Číslo

10

Strany od–do

1785–

Počet stran

7

BIBTEX


@article{BUT43698,
  author="Miloš {Šeda}",
  title="Solving Resource-Constrained Project Scheduling Problem As a Sequence of Multi-Knapsack Problems",
  journal="WSEAS Transactions on Information Science and Applications",
  year="2006",
  volume="3",
  number="10",
  pages="7",
  issn="1790-0832"
}